Milestones associated with the commissioning and installation of the sculpture
MilestoneDeadline
Procurement: open call for Artists - 6-week submission periodSeptember - November 2023
Procurement: Shortlisting and Panel decisionNovember 2023
Announcement and commissioningNovember 2023
Development phaseNovember 2023 - April 2024
MWG decision on location of each piece of artworkNovember 2023
ManufacturingApril - August 2024
InstallationTBC in line with Market Place Public Realm Programme
CompletionTBC in line with Market Place Public Realm Programme