Five-year housing land supply position statement (as at 01 April 2024)

Calculation of the five-year housing land supply position

Tables 2 and 3 summarise the sources of supply for the five-year period (2024 to 2029) and the total number of years of deliverable housing land. A full breakdown of each individual site assessed within this position statement can be accessed below: 

Table 2: Summary table of sources of deliverable housing supply 2024 to 2029
Sources of supply2024-292025-262026-272027-282028-29
Major sites (sites of 10 or more dwellings, or 0.5ha or more) with full or detailed planning consent27327634529071
Small sites (sites below 10 dwellings or 0.5ha) with planning consent (full/outline)11210649259
Allocations (Local Plan)00094210
Major sites (sites of 10 or more dwellings or 0.5ha or more) with outline planning consent00148088
Windfall00163264
Subtotals385382424521442
Grand total (2024-25 to 2028-29)2,154
Table 3: Number of houses and years identified against the five-year requirement
Calculation codesFive-year housing land supply componentNumber of dwellings
AFive-year supply requirement including 5% buffer1,850
BAnnual requirement (A divided by 5)370
CTotal number of units identified2,154
DNumber of units above or below five-year supply requirement (C minus A)304
ENumber of years of deliverable housing land (C divided by B)5.82

Results summary

This position statement has identified sites within the borough of Great Yarmouth that are capable of delivering 2,154 new homes within the next five-year period (April 2024 to March 2029). The target requirement over this period is 1,850 therefore this represents an over provision of 304 new homes.

In conclusion, this statement identifies sites capable of delivering 5.82 years of housing land supply.

Last modified on 20 December 2024